The CT-TAE certification is ideal for professionals who are involved in test automation, such as test automation engineers, test automation architects, and test automation managers. Certified Tester Test Automation Engineer certification provides validation of an individual's expertise in test automation, and helps to demonstrate their commitment to the field of software testing. The CT-TAE certification is also useful for individuals who are looking to advance their careers in the field of software testing.
The CT-TAE certification exam consists of 40 multiple-choice questions that must be completed within 90 minutes. CT-TAE exam is divided into three sections: the first section covers test automation design and planning, the second section covers test automation implementation, and the third section covers test automation maintenance and management. CT-TAE exam is designed to test the candidate's ability to apply their knowledge of test automation concepts and techniques in real-world scenarios. Upon passing the CT-TAE certification exam, professionals will be able to demonstrate their proficiency in test automation and enhance their career prospects in the field of software testing.
NEW QUESTION # 45
You are using a gTAA to create a TAS for a project. The TAS is aimed specifically at automating a suit of existing manual test cases for standalone desktop applications. All the interfaces between the TAS and SUT will be from the CUI of the application.
Which of the following layers of the gTAA should you focus on for the TAS?
- A. The Test Execution layer
- B. The Test Definition layer
- C. The test Generation layer
- D. The Test Adaption layer
Answer: D
NEW QUESTION # 46
Which of the following BEST describes why it is important to separate test definition from test execution in a TAA?
- A. It allows developing steps of the test process without being closely tied to the SUT interface.
- B. It allows specify test cases without being closely tied to the tool to run them against the SUT
- C. It allow choosing different paradigms (e.g event-driven) for the interaction TAS and SUT
- D. It allows testers to find more defects on the SUT
Answer: B
NEW QUESTION # 47
You are working as a TAE for a company who are re-designing their website. The new website provides information for customers and there are two minor features being developed:
1) Request a newsletter
2) Ability to contact the organisation with a question or comment
The website must be "mobile friendly" and available on all major web browsers.
You have been tasked to provide an automated solution for web browsers only and to concentrate on the two minor features.
What would be a KEY challenge with automation in this context?
- A. The benefits of automation might not be achieved for many years due to the complexities of the SUT and automation solution.
- B. Automation might not be possible on the mobile devices.
- C. Because there is a high level of intrusion there may be many false alarms.
- D. A low level of intrusion is likely from use of existing UI elements, but depending on the solution this might be more complex than a higher level of intrusion.
Answer: A
NEW QUESTION # 48
If you are tracking the frequency that a test automation code reports a defect that is not really a defect, what metric are you gathering?
- A. Automation code defect density
- B. Trend metrics
- C. The number of false-fail results
- D. Tool scripting metrics
Answer: C
NEW QUESTION # 49
When if the BEST time for automation to consider legal and/or standard requirements for a SUT?
- A. When designing a TAA
- B. When developing a TAS
- C. When implementing the SUT
- D. When designing a TAF
Answer: C
NEW QUESTION # 50
A project consists of distributed teams working in a 24-hour environment, where activities happen at all hours of the day. This project adopts a CI (Continuous Integration) process when developer check-in code and consists of automated activities that include generating a build and deploying it to a test environment. Automated integration tests are run multiple times a day. The project have asked for a report containing the automation test results for every build, which must be available 24/7 to the project team.
Which of the following would be the BEST way to automatically provides this report?
- A. Store the execution results of the integration tests for the last build to a database (without overwriting the results from the previous builds), use this database to automatically update a dashboard containing the build history and test results accessible to the project team.
- B. Store the execution result of the integration tests for the last build to a database (overwriting the results from the previous build), automatically create a test execution report for this build send It via e-mail to the project team
- C. Store the code coverage results of the integration tests for the last build to a database (without overwriting the results from the previous builds). And automatically create a chart showing the trend in code coverage and send via email to the project team.
- D. Store the execution results of the integration tests for the last build to a database (without overwriting the results from the previous builds). Automatically create a test execution report for this build and send it via e-mail to the project team
Answer: A
NEW QUESTION # 51
A major component of your organisation's Test Automaton Solution (TAS) is a popular open-source third-party capture-replay tool for automated functional testing.
Which two of the following must the Test Automation Engineer (TAE) ensure happens for this TAS?
a) The third party tool is placed under configuration management control.
b) The annual support and maintenance costs are agreed with the tool's vendor.
c) It is Important to obtain information about updates and new versions of the tool so that the third party tool is kept up to date.
d) Ensure that the TAS test scripts are integrated into the tool's framework.
e) Ensure that no changes are made to the tool, because modifications are not allowed for third party products.
- A. a and b
- B. a and c
- C. d and e
- D. c and d
Answer: A
NEW QUESTION # 52
You are evaluating several test modelling tools and are wanting to automatically generate test cases within the tool where many different combinations of input data are created.
You are then wanting to export the test cases into a csv file which can then be read by a functional test execution tool using a data-driven or keyword-driven scripting method.
You have investigated several tools and there is only one tool that provides all the necessary features defined by your team with the exception of the export facility. It does not provide an export into either .xls or .csv formats.
What would be the BEST next step regarding the selection of this tool?
- A. Consider another tool that is more "fit for purpose" and has all the features required.
- B. Purchase this tool and generate the .csv file manually.
- C. Explore the possibility of creating your own export facility.
- D. Ask the vendor and use forums to see if a solution is available or going to be available in the future.
Answer: D
NEW QUESTION # 53
In order to achieve re-use of a TAS, where SHOULD the design for reuse occur?
- A. At the TAA level
- B. At the TAS level
- C. At the framework level.
- D. At the code level
Answer: B
NEW QUESTION # 54
A regression test suite consist of 500 test cases which are all executed manually. The business case for a pilot project is based on the adoption of test automation using a commercial tool that will reduce the execution time by a factor of 90% for 100% of the tests in the regression test suite. The pilot project lasted one month ( as planned) and you are currently its results. At the end of the pilot project, 40% of the regression tests have been automated and their execution time has been reduce by 60%.
Which of the following statements is TRUE in this scenario?
- A. The target defined for the business case is too accurate -it should not be measureable
- B. The project selected for the pilot is too critical -if should not be too critical or too trivial
- C. The duration of the pilot project was too short -it should last unit the success factors are achieved
- D. The target defined for the business case seems difficult to hit - it should be realistic
Answer: D
NEW QUESTION # 55
You have been asked to automate a set of functional tests at system Test level via the CLI of the SUT for the first release of a software system. The automated tests will be delivered to the learn in change of maintenance testing, who will use them for part of the regression testing. They have the following requirements.
1. The automated tests must be as fast and cheap to maintain as possible
2. The cost of adding new automated tests must be as low as possible
3. The automated tests must have a high level of independence from the tool itself Which of the following scripting techniques would be MOST suitable?
- A. Data-driven scripting
- B. Structure scripting
- C. Keyword-driven scripting
- D. Linear scripting
Answer: B
NEW QUESTION # 56
Which of the following describes how a test execution report is likely to be used?
- A. To understand which test step caused the failure in a test case
- B. To record how a test case failure has been fixed
- C. To measure coverage of the test basis by a test suite
- D. To identify problematic areas of the SUT by keeping a history showing which test cases fail the most
Answer: D
NEW QUESTION # 57
You are working on a web-based application called Book Vault that allows people to upload books and order books. This application must be available on all major browsers.
You have been testing the application manually and management have asked you to consider automating some of the tests.
You have investigated a number of commercial and free tools which can automate tests at a web browser level and one tool in particular meets your requirements and you have implemented a trial version.
You have basic programming skills and the main goal is to automate a few functional tests to see if the tool is compatible with the application and can recognise the objects and controls.
Which scripting technique would be MOST suitable in this scenario in order to meet the objectives?
- A. Data-driven scripting
- B. Model-based scripting
- C. Structured scripting
- D. Capture-replay scripting
Answer: D
NEW QUESTION # 58
Which of the following statements BEST describe aspects of the SUT to consider when designing a TAA?
- A. All the interaction between SUT and TAS should be logged with the highest level of detail
- B. All the interface of the SUT affected by the tests should be controllable by the TAA
- C. All the external test interfaces of the SUT should be removed prior to the product release
- D. All the internal test interfaces of the SUT should be removed prior to the product release
Answer: A
NEW QUESTION # 59
You have implemented a keyword-driven scripting framework, which uses a test execution tool to run the tests. This has been in use for the past year and all of the teams now use this framework as the standard approach for test execution.
The teams all work on different aspects of the SUT and they have all experienced significant benefits in the use of this scripting framework. However, on closer examination, you have discovered that there are numerous instances where the teams have the same functionality to test but are using different keywords.
One of your objectives for improvement is to create consistency among the teams.
What is the BEST way to handle this situation?
- A. Do nothing, each team are working in isolation and they are all experiencing significant benefits in the way they are currently working.
- B. Create a central library of keywords and associated definitions for each team to use.
- C. Provide each team with a set of guidelines and naming conventions for keywords.
- D. Move to a model-based approach to scripting where the models include the keywords.
Answer: B
NEW QUESTION # 60
Your organisation has successfully implemented a Test Automaton Solution (TAS) for a new project which has since been delivered into production via a number of sprints. A series of maintenance releases are now planned.
Some improvements were made to the Test Automation Architecture (TAA) as a result of feedback from the early sprints. The TAA improvements affected the TA, and the TAS was changed for the final sprint.
The new version of the TAS was generally well received but some performance and usability issues were encountered with the TAS which have yet to be addressed.
The test automation engineers supporting the maintenance releases must decide whether to use the enhanced TAS or the version that was used successfully for previous sprints.
What is the BEST action to take next?
- A. Use the new version of the TAS for the first maintenance release on a trial basis. If issues are encountered, switch to the previous version for later releases until the issues are resolved.
- B. Perform an analysis of risks versus benefits for the enhanced TAS and then decide which version to use.
- C. Use the new version because, despite some issues, it works, and the live system should not be tested using a different TAS.
- D. Use the previous version because this was proven to work. It will be too risky to use the new version, with unresolved issues, for a live system.
Answer: A
NEW QUESTION # 61
......
The CT-TAE certification exam is a three-hour, closed-book exam that consists of 40 multiple-choice questions. CT-TAE exam covers topics such as test automation process, test automation framework, test automation design, and test automation implementation. CT-TAE exam is designed to test the candidate's understanding of the concepts and principles of test automation.