Try Before You Buy

Download a free sample of any of our exam questions and answers

  • 24/7 customer support, Secure shopping site
  • Free One year updates to match real exam scenarios
  • If you failed your exam after buying our products we will refund the full amount back to you.

New (2022) Download free C_TS412_1909 PDF for SAP Practice Tests [Q22-Q44]

Share

New (2022) Download free C_TS412_1909 PDF for SAP Practice Tests

100% Free C_TS412_1909 Files For passing the exam Quickly


SAP C_TS412_1909 Certification Exam Topics:

Topic AreasTopic Details, Courses, Books
Resources > 12%

Describe how the Resource Planning process integrates with HCM

Dates > 12%

Describe the importance of various dates which can be tracked for projects

Reporting < 8%

Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports

Material > 12%

Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement

Project Structures > 12%

Name the components of Work Breakdown Structure, Network and activities, Milestones



SAP S/4HANA Project Systems Certification Exam Details:

Sample QuestionsSAP S/4HANA Project Systems Certification Sample Questions
LevelAssociate
Duration180 mins
Schedule ExamSAP Training
Exam NameSAP Certified Application Associate - SAP S/4HANA Project Systems
Passing ScoreC_TS412_1909 - 51%

 

NEW QUESTION 22
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.

  • A. An activity-account-assigned network that is assigned to a sales order item
  • B. A dynamic item processor (DIP) profile with the appropriate settings
  • C. A header-account-assigned network that is assigned to a sales order item
  • D. Released WBS elements, activities, and/or activity elements

Answer: B,D

 

NEW QUESTION 23
Material
How can the system activate requirements (such as reservations or purchase requisitions)?
Note: There are 2 correct answers to this question

  • A. When releasing a network or an activity
  • B. Using a standard milestone activity
  • C. Automatically, using the requirement date and the replenishment lead time
  • D. Immediately, by saving the project

Answer: A,C

 

NEW QUESTION 24
You are working with networks and WBS elements. Which of the following statements applies

  • A. You can assign the network header to multiple WBS elements
  • B. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • C. You can reassign an activity from one network to another
  • D. You have to maintain a network profile in the project profile

Answer: B

 

NEW QUESTION 25
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

  • A. The material master of the component must permit project stock management
  • B. The network activity is assigned to a WBS element
  • C. The Project Stock indicator is set in the project definition (non-valuated or valuated)
  • D. A procurement indicator must be assigned to the activity
  • E. The network is assigned to a sales order item

Answer: A,B,C

 

NEW QUESTION 26
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question

  • A. Shift activities backward or forward on the time axis where more capacities are available
  • B. Trigger automatic capacity leveling inside the project planning board
  • C. Maintain subordinate internal activity elements assigned to other work centres
  • D. Increase the capacities of the work center in the project planning board.

Answer: A,C

 

NEW QUESTION 27
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.

  • A. Use an offset of two days for milestone date.
  • B. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
  • C. Use an offset of two days for the requirement date of the material component
  • D. Use an offset of two days for the relationship of both activities.

Answer: A,D

 

NEW QUESTION 28
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well.
Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. The system automatically creates a new purchase requisition with the difference to the original quantity
  • B. The purchase order is updated automatically to match the new quantity while saving the project.
  • C. A workflow can be triggered to inform the purchasing group.
  • D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)

Answer: B

 

NEW QUESTION 29
How can you grant individual authorization for WBS elements and networks?

  • A. Activate access control lists (ACL) for the user master record.
  • B. Activate access control lists (ACL) for the project profile and the network profile.
  • C. Set the system status to "Lock Master Data".
  • D. Define a user status to lock the business transaction Update Project.

Answer: B

 

NEW QUESTION 30
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?

  • A. Enter February 10 as fixed date
  • B. Enter an offset of -18 days to the finish date of the activity
  • C. Enter 10 days as duration
  • D. Enter an offset of 10 days to the start date of the activity

Answer: A

 

NEW QUESTION 31
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.
What planning method for basic dates do you use ?

  • A. Free planning
  • B. Bottom-up
  • C. Top-down
  • D. Strict bottom-up

Answer: B

 

NEW QUESTION 32
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
  • B. Set up the requirement date manually as February 5.
  • C. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
  • D. Set up the requirement date aligned with the activity start date and an offset of 5 days

Answer: C

 

NEW QUESTION 33
Which of the following business processes do NOT lead to the booking of actual costs to an object? Note: There are2 correct answers to this question

  • A. Recording of external services in the service entry sheet
  • B. Goods receipt into unvaluated project stock
  • C. Goods receipt into valuated project stock
  • D. Goods receipt of a non-stock item

Answer: A,D

 

NEW QUESTION 34
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Structure overview
  • B. Individual overview capacity requirements
  • C. Extended capacity evaluation
  • D. Capacity load work center view
  • E. None

Answer: B

 

NEW QUESTION 35
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. WBS elements
  • B. Project definitions
  • C. Activities
  • D. Tasks

Answer: A

 

NEW QUESTION 36
You are working with networks and WBS elements. Which of the following statements applies?

  • A. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.
  • B. You can assign the network header to multiple WBS elements.
  • C. You have to maintain a network profile in the project profile.
  • D. You can reassign an activity from one network to another.

Answer: B,D

 

NEW QUESTION 37
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Vendor
  • B. Overall limit (maximum value of all unplanned services)
  • C. Service specification
  • D. Service purchase order number
  • E. Material master within service specification

Answer: A,B,C

 

NEW QUESTION 38
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.

  • A. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
  • B. The material master is set to external procurement.
  • C. The material is assigned to the activity as a non-stock material.
  • D. The availability check for material components indicates missing parts.

Answer: A,D

 

NEW QUESTION 39
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the network activity
  • B. In the WBS element
  • C. In the material master
  • D. In the project definition

Answer: D

 

NEW QUESTION 40
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?

  • A. Calculation of actual values
  • B. Creation of purchase orders
  • C. Activity allocation
  • D. Goods receipt for purchase orders

Answer: B

 

NEW QUESTION 41
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.

  • A. Cancel goods issue
  • B. Generate delivery
  • C. Generate purchase requisition
  • D. Confirm production order
  • E. Stock transfer posting

Answer: B,C,E

 

NEW QUESTION 42
Which of the following apply to dynamic item processor (DIP)? Note: There are 3correct answers to this question.

  • A. Sales prices are maintained in the DIP profile
  • B. Material determination is mandatory
  • C. Sources can be based on line items
  • D. Usage of cost elements is mandatory
  • E. DIP is used to create a quotation

Answer: B,D,E

 

NEW QUESTION 43
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

  • A. In the project type
  • B. In the project version
  • C. In the project profile
  • D. In the project definition of a standard WBS
  • E. In the operative WBS element

Answer: C,D,E

 

NEW QUESTION 44
......


SAP C_TS412_1909 Exam Description:

The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.

 

C_TS412_1909 Premium Exam Engine - Download Free PDF Questions: https://examtorrent.braindumpsit.com/C_TS412_1909-latest-dumps.html